Project milestones

June 27, 2011


NINA acquired the property.
Read More

October 12, 2011


Building permit issued by City of Hartford. Days elapsed since acquisition: 107.
Read More

December 6, 2012


Certificate of occupancy issued by the City of Hartford. Days elapsed since building permit issued: 421. Total days elapsed since acquisition: 528.
Read More

April 26, 2013


NINA sold house to new homeowners. Days elapsed since certificate of occupancy issued: 141. Total days elapsed since acquisition: 669.
Read More