190

Progress at 279 Farmington

David
279 Farmington Avenue
8/6/2025

More framing.



Meanwhile, out in the garden

David
102 Huntington Street
8/6/2025

We had formed a partnership with Our Piece of the Pie to maintain the garden this summer, as OPP has a workforce development program in landscaping, but unfortunately OPP became overwhelmed by helping students who had been signed up to work this summer through Blue Hills Civic Association.  I think, however, that the garden looks quite nice, overgrown as it is.



Around front, work is underway on the porch

David
102 Huntington Street
8/6/2025

A lot of activity on the porch!



Back deck removed at 102 Huntington

David
102 Huntington Street
8/6/2025

The exterior door to the basement, which was under the deck, has also been removed and bricked up.  Actually, “cinder blocked up.”  The cinder blocks beneath the deck were original – maybe?  They predate NINA, and it seems a good guess that they were installed the sun room was added to the house in the 1940s.



Update on the front door of 102 Huntington Street

David
102 Huntington Street
8/1/2025

Wow!  Won’t be long now.



A tree grows on 285 Farmington

David
285 Farmington Avenue
8/1/2025

The view from the window at 279 Farmington, which can at last be opened.



Progress at 279 Farmington

David
279 Farmington Avenue
8/1/2025

Framing on the first floor.  Work inside the front porch.  Framing starting on the second floor.  View of the third floor.